# Sanity review: coverage and consistent definitions

Checked November 3, 2026. This pass checks the displayed selections and calculations across charts, profiles and exports, with primary-source checks on the affected financial figures and agreements. It is not an independent re-verification of every historical source row.

## Material omissions filled

| Relationship | Evidence retained | Interpretation |
|---|---|---|
| Meta → AMD | [February 24 agreement](https://ir.amd.com/news-events/press-releases/detail/1279/amd-and-meta-announce-expanded-strategic-partnership-to-deploy-6-gigawatts-of-amd-gpus) | Up to 6GW across generations; price and native count undisclosed. [October 27 update](https://ir.amd.com/news-events/press-releases/detail/1302/amd-and-meta-advance-strategic-partnership-to-power-metas-superintelligence-infrastructure) confirms initial Helios testing, without quantifying a production fleet. |
| Meta → NVIDIA | [February 17 announcement](https://investor.nvidia.com/news/press-release-details/2026/Meta-Builds-AI-Infrastructure-With-NVIDIA/) | Multi-generation GPU/CPU/network partnership. Qualitative volume and no disclosed price; no invented numeric chip count. |
| Meta → Broadcom | [April 14 announcement](https://about.fb.com/news/2026/04/meta-partners-with-broadcom-to-co-develop-custom-ai-silicon/) | Initial MTIA commitment exceeds 1GW within a multi-GW rollout; distinct from online power. |
| NVIDIA → IREN | [May 7 agreement](https://irisenergy.gcs-web.com/news-releases/news-release-details/iren-secures-34bn-ai-cloud-contract-nvidia) | Approximately $3.4B over five years for managed Blackwell cloud services, within approximately 60MW of existing space. Equity rights and the broader infrastructure collaboration are separate. |
| AMD → Core Scientific | [July 28 results](https://www.sec.gov/Archives/edgar/data/1839341/000183934126000013/q22026corescientificinc-ea.htm), [partnership](https://investors.corescientific.com/news-events/press-releases/detail/138/core-scientific-and-amd-announce-infrastructure-partnership) | Approximately 530MW, 15-year initial agreements and more than $14B of potential base revenue. The expansion opportunity to 2.5GW is separate. Powered infrastructure, not a GPU rental. |

Published Ascend 910B/910C quotes were already in the source data but hidden by the price chart's fixed chip list. They are now visible and have a Huawei filter. All providers with retained power observations appear; the previous twenty-row cutoff is removed. Sparse Azure and Alibaba revenue histories now show their available observations rather than disappearing entirely.

## Inconsistencies corrected

- **Revenue:** chart and profile now use the same explicit segment: IREN AI Cloud Services, Applied Digital HPC Hosting, Core Scientific colocation and TeraWulf HPC leasing. Earlier company totals included mining or other businesses. Applied Digital's hosting revenue includes fit-out services and recoveries; it is not all recurring rent. [IREN](https://www.sec.gov/Archives/edgar/data/1878848/000187884826000051/irenreportsfy26results.htm), [Applied Digital](https://www.sec.gov/Archives/edgar/data/1144879/000114487926000057/apldq127earningsrelease.htm), [Core Scientific](https://www.sec.gov/Archives/edgar/data/1839341/000183934126000013/q22026corescientificinc-ea.htm), [TeraWulf](https://www.sec.gov/Archives/edgar/data/1083301/000108330126000162/a_wulfearningsreleaseq22026.htm).
- **Microsoft backlog:** $683B total RPO and $677B commercial RPO are both valid September figures. Profiles and growth now consistently select commercial RPO. The [10-Q](https://www.sec.gov/Archives/edgar/data/789019/000119312526436133/msft-20260930.htm) explicitly distinguishes both; neither is Azure-only backlog.
- **Revenue history:** later restated Nebius continuing-operations figures replace original Toloka-inclusive observations in the plotted series. Alibaba's old and reorganized segments are not joined into one growth line. Azure's prior-year comparative uses the issuer's recast basis, without estimating missing quarters. [Microsoft release](https://www.microsoft.com/en-us/Investor/earnings/FY-2027-Q1/press-release-webcast).
- **Power:** mining assets under management, connected power, individual site phases, company IT power, gross power and billable power no longer form a common provider trend. IREN's reported Horizon 1 phase is shown as an incomplete site observation. Company announcements and Epoch estimates remain separate for SpaceX. A single observation produces a point, not an invented trend.
- **Core Scientific timing:** 225MW is the March 31 comparative in the July release; 243MW is the May 6 operating update. Both are retained at their dates. [May release](https://www.sec.gov/Archives/edgar/data/1839341/000162828026031246/q12026corescientificinc-ea.htm), [July comparative](https://www.sec.gov/Archives/edgar/data/1839341/000183934126000013/q22026corescientificinc-ea.htm).
- **Lease economics:** three CoreWeave–Core Scientific tranches now join the initial tranche as powered-space leases. Their low $/kW-month figures no longer masquerade as chip-inclusive compute prices. Medians use the standard even-sample calculation; unmatched medians no longer imply a measured chip-cost decomposition.
- **Inference share:** Together's serverless API revenue share is removed from the inference-versus-training plot. Dedicated clusters also serve inference, so the share cannot answer that question. NVIDIA is grouped with suppliers. Future market estimates explicitly say “forecast.”
- **Daily prices:** explanatory percentages are generated from the same live records as the table. Previously, a static B200 decline of 6.3% contradicted the refreshed feed. Provider profiles use the common end-2025 Epoch date, matching the main fleet view. Source links were added to remaining chart tooltips.

The data rules are shared by the summary and website build. Regression checks enforce one scope and power basis per growth series, agreement between chart endpoints and profiles, correct lease classification and preserved bounds. Raw historical records are retained; corrections use the override layer.

## The remaining elephants in the room

1. **Installed and usable supply.** Owner shipment estimates and selected site power do not reveal a complete current online fleet, active utilization or inference-ready capacity. Hosts and clouds can describe the same racks. A global supply-demand balance is still unsupported.
2. **Comparable token demand.** Companies use overlapping scopes and usually omit input/output, cache, reasoning and modality accounting. Anthropic has no comparable public absolute total in the retained evidence; several other totals are historical or narrow subsets. There is no defensible additive global token total here.
3. **Financing and profitability.** Nominal multi-year deals do not establish current revenue, cash collected, credit exposure or project funding. A full balance-sheet/cash-flow and customer-concentration analysis remains absent. Cancellation rights, delivery conditions, leases and equity arrangements matter independently.
4. **The physical bottlenecks.** HBM, advanced packaging, networking, cooling, interconnection and commissioning can each constrain delivered useful compute. The current ledger has selected evidence, not a complete reconciliation from chip production through powered racks. MTIA and domestic Chinese accelerators also lack comparable owner-level counts.
5. **Cost of useful work.** The capacity calculator is a conditional extrapolation from particular coding traces and serving configurations. Model quality, workload mix, latency targets, cache reuse and reliability prevent treating its rack ratio as a universal cost advantage. Negotiated rates and matched hardware resale transactions are also incomplete.

These gaps are now explicit research priorities in [the coverage queue](GAPS.md). They should guide the next data pass, not be filled with numerical guesses.