# Remaining evidence gaps

Updated November 3, 2026. The [latest consistency review](SANITY-2026-11-03.md) fills five material agreements and fixes mixed definitions. The largest remaining omissions are measured utilization, comparable token accounting, financing and cash flow, and a complete chip-to-powered-rack supply chain. The public-source investigation does not close the full evidence queue.

| Priority / gap | What is now supported | What remains open |
|---|---|---|
| P0 / comparable demand | Dated provider, API, router and country disclosures; period conversions preserve bounds. | Common input/output/cache/reasoning accounting, current absolute lab totals and a non-overlapping global total. |
| P0 / financing and delivered utilization | Selected company filings, lease terms and funding announcements. | Comparable balance-sheet/cash-flow and customer-concentration analysis; actual occupancy, utilization and realized returns. |
| P0 / G01: price shock | Same-SKU/region Nebius B200/B300 hourly posted panels; dated one-year benchmark changes. | Dated GB200 provider panel; trade volumes and market-wide representativeness. Static −22.6% headline has no observation date. |
| P0 / G02: commitment pricing | Primary three-year retail reservations; primary AMD advertised floors. | Current negotiated GB200/GB300/AMD three-year distributions with scale, prepay and delivery terms. |
| P0 / G03: enforceable commitments | Updated buyer filing; minimum, conditional and cancellable amounts distinguished. | Global overlap netting, remaining guaranteed cash after cancellation and allocation across economic layers. |
| P0 / G04: actual versus forecast | SpaceX latest actual and separate company targets; hypothetical Microsoft arrangement stays a scenario. | Signed evidence for the hypothetical deal and a full phase-by-phase ramp. |
| P0 / G05: comparable power | Company nameplate, Epoch IT estimates, stock/flow and geographic differences disclosed. | Complete provider/site crosswalk and measured common-basis online power. |
| P1 / G06: supply bridge | DayOne/QTS hosts and selected dated site phases added. | Reconciliation to the full 2027–28 annual global additions forecast. |
| P1 / G07: policy impact | Dated state directives, municipal decisions and agency registry leads. | Current release/exemption status and demonstrated supplier-specific MW/delay impacts. |
| P1 / G08: chips versus halls | Vendor memory and packaging milestones sourced. | Accelerator mix, HBM quantities, rack/network commissioning and an auditable MW balance. |
| P1 / G09: hardware prices | Lagged fixed-basket resale index and configuration-sensitive examples. | Current matched OEM and completed resale panels, particularly Blackwell. |
| P1 / G10: native fleet counts | Owner/user/cluster overlaps disclosed; AMD/TPU/Trainium native units retained. | Current installed generation counts for many providers; MTIA and domestic Chinese owner-level counts. Shipments are not online fleets. |
| P2 / G11: useful work | Public calculator assumptions inspected and identified as assumptions. | Measured workload throughput, reliability and service-target comparisons. |
| P2 / G12: ownership economics | Public model scope and arithmetic dependencies identified. | Entitled model export and reconciliation of capex, finance, useful life, residuals, occupancy and workload output. |
| P2 / G13: source conflicts | Both claims, dates and display choices accessible by hover, focus and tap. | Reconciliation of Johor capacity, analyst lease totals and SpaceX article ARR inconsistencies. |
| P2 / G14: China comparability | Named commissioned cluster and primary chip shipment/design evidence. | Binding same-region H20/Ascend contract prices with matched tax, networking, scale and term. |

The source audit and individual chart notes state the corresponding evidence limits. Missing values remain missing.